From tragedy to transformation: The story of the Turkey Creek Flood Damage Reduction Project

News originally published by

DVIDS - Georgia

Historically speaking, Turkey Creek had been a consistent menace to the region since settlers began to inhabit its banks in the mid-19th century. Even after locals completed a tunnel in 1919 to divert, or shortcut Turkey Creek to the Kansas River away from inhabited areas, the major floods of 1935, 1944, 1958, 1961, 1977, 1983, 1986, 1993 and 1998 still overflowed its banks causing extensive damages.

For those living through the second half of the 20th century, Turkey Creek has been a repeated source of flooding for businesses, residents and critical infrastructure near its banks as it winds through sections of the Kansas City Metropolitan area. Major floods of the Kansas River such as the July 1951 flood, backed water up into many of the same areas flooded by Turkey Creek as far upstream as the basement of Union Station.

While improvements to the federal Central Industrial District, or CID Levee reduced flood risk from the Kansas River by the late 1970’s, overflows from Turkey Creek remained unaddressed.

The 1998 floods were particularly tragic in corridors of Johnson and Wyandotte counties, causing an estimated $12 million in damages that year, according to historical project documentation. For the overflow area of Turkey Creek along Southwest Boulevard and within CID, flood levels were little different from those five years earlier on July 10, 1993.

The persistent threat to the area underscored the need for a long-term solution to a problem that crossed state lines. Reflecting on the 1993 flood, former Mayor of Kansas City, Missouri, Emanuel Cleaver II, recalled the toll repeated flooding took on local business owners at a 2009 event to celebrate the rehabilitation of a tunnel built in 1919 that is a part of the Turkey Creek flood risk management plan.

“In May 1993, I was on the cover story of Jet Magazine that focused on the flooding. I came down here on a boat,” said Cleaver, who now represents Missouri's 5th Congressional District in the U.S. House of Representatives. “I saw businessmen and women weep because they had again lost their life savings that they put into these businesses.”

The recurring catastrophes caused by Turkey Creek leaving its banks made clear that addressing flood risk would require more than a single construction project. It would take engineering infrastructure improvements, sustained federal and local investment, and years of collaboration among local, state, and federal agencies and the affected communities sharing the risk.

The result was the Turkey Creek Flood Damage Reduction Project, a multidecade effort led by the Kansas City District, U.S. Army Corps of Engineers, in partnership with the city of Kansas City, Missouri, and the Unified Government of Wyandotte County and the city of Kansas City, Kansas.

“The project was designed to safely pass 24,300 cubic feet per second, a larger [flooding] event than the record October 1998 flood,” Chance Bitner said, who is the district branch chief for the Hydrologic Engineering Branch section. “The project and the tunnel to the Kansas River were constructed in eight phases.”

A growing metropolis shaped the creek

Turkey Creek drains an urbanized basin of approximately 23 square miles, where water from the main channel and surrounding areas converge near the Kansas and Missouri state boundary. The flood threats the creek poses come from two primary sources: Turkey Creek overflowing its banks and heavy runoff flowing down the hillsides above Southwest Boulevard.

Therefore, Turkey Creek’s history is intimately tied to the commercial, industrial and residential development of areas of significance to the Kansas City metropolitan area.

“One fun fact is that Turkey Creek historically flowed through the West Bottoms and current Central Industrial District levee area to the Missouri River,” Bitner said. “Early settlers built homes on both banks of Turkey Creek and had a bridge so that they could reach the current downtown area of Kansas City. It met the Missouri River at the current Santa Fe Pump Station on the CID’s Missouri levee until it shifted to the Kansas River at the current outfall for OK Creek during the 1844 flood.”

Historical maps dating from 1855 through 1887 show this progress, with a railroad operation occupying the valley by 1870 and Southwest Boulevard appearing by 1887. By the early 1900s, the West Bottoms were heavily developed, making it vulnerable to flooding since it was on the doorstep of historic Kaw Point.

As the landscape quickly transformed from agrarian to urban in the early stages of the industrial revolution, the creek was increasingly constrained by the expansion of infrastructure.

“The tunnel was completed in 1919 to divert water to the Kansas River about a mile further upstream to reduce flood damages to that area. This is why the flows from Turkey Creek are also tied to the CID unit of the current Kansas City's Levees system,” Bitner said.

Almost instantly, the tunnel became the most critical component of the drainage system, but decades of deterioration and changes to the surrounding channel eventually created new, unintended challenges.

But rehabilitating the original Turkey Creek tunnel, constructed between 1918 and 1919, was by far the most difficult, according to former Kansas City District Commander, Col. A. Roger Wilson Jr.

“We found severe and accelerated tunnel liner and floor deterioration, erosion to depths of 20 feet on the floor of the tunnel, and sidewall erosion that exceeded 60 feet into the bedrock,” he said. “The project has been an experience with more than its share of unique financial, environmental, engineering and political challenges.”

The rehabilitation required extensive work inside the approximately 1,300-foot-long, 28-foot-diameter existing structure. Contracted construction crews removed approximately 10,000 tons of deteriorated material and placed 6,000 cubic yards of concrete. They also added around 335,000 pounds of reinforcing steel, 1,100 cubic yards of shotcrete and 640 cubic yards of grout.

Additional modifications to the channel came when Interstate 35 began construction in the 1960’s. Meanwhile, the area's continued development increased the importance of managing stormwater through a corridor already crowded with businesses, roads, the railroad, and other critical infrastructure.

While speaking at the 2009 event, Sam Brownback, former U.S. Senator for Kansas who helped secure federal funding for improvements to the aging tunnel, said the floods of 1993 and 1998 reinforced the need for a comprehensive approach that could potentially alleviate some of the flooding risks.

“This area has flooded way too many times for way too long and it’s hampered the development of this area way too much, period,” he said.

Melissa Corkill, who began her USACE career with the district in 2005 and served as the project manager on the complex flood risk reduction project from 2009 to 2012, described the project as one of the most fascinating engineering efforts of her career.

Outside of the underground tunnel, the project involved an extraordinary combination of infrastructure that included a levee; a walled channel; the rerouting of railroad and roadway bridges as well as major stormwater drainage and conveyance systems.

But for Corkill, the most lasting impression wasn't the engineering alone.

"Each of these components came with its own engineering challenges, construction complexities and coordination requirements," Corkill said. "But as fascinating as the engineering has been, what made the biggest impact was the people."

One system, multiple flood threats

As the system progressed in complexity and efficiency, the flood risk switched from the surrounding areas to the actual workers who were actively transforming Turkey Creek, through what Bitner called, “excessive-flow events.”

This phenomenon repeatedly interrupted construction and required crews to be wary of the creek's changing conditions, which is why planning for construction required lots of work to figure out how to divert and account for even just the base flow in the creek, let alone during heavy downpours that contributed to the creek’s urban lore of having unpredictable water levels afterwards.

“Dealing with high water events was challenging throughout, dating back to managing water to keep the tunnel dry for repairs during Phase I,” Bitner said.

Immediately, he turned to an example from August 2017, when heavy rain changed work site conditions for contractors fairly quickly.

“Staff from my office visited the project site to collect high water marks and noted a tree limb sitting on top of an excavator that had been working down in the channel and was left there after the flood waters receded near the tunnel. This further indicates how quickly and how dramatically water can rise," he said.

Overall, the Turkey Creek Flood Damage Reduction Project was designed to address the many ways floodwater can reach vulnerable, low-lying areas within the creek’s footprint.

So, rather than relying on a single structure like the tunnel, the project combines improvements to the creek channel and other infrastructure that intercepts or redirects runoff, Bitner stated.

“Major features include a walled channel, a 90-foot-wide concrete channel that is 1,000 feet long; the restored channel at 60 to 100 feet in width and 1,734 feet in length; over 5,000 feet of benched and trapezoidal channel at an 86-foot width; creek bank stabilization in specific areas; a 20-foot-wide, 535-foot-long channel slot to improve flow into the tunnel at the downstream end of the project; and three major hillside interceptor systems: the Cherokee, Rainbow, and Missouri,” he said.

Each additional feature outside of the rehabilitation of the tunnel serves a purpose within the larger system. But there is even more.

“We also constructed a total of 6,800 feet of levees with nine drainage structures, 14 acres of environmental enhancement area and one stoplog closure,” Bitner said. “Additionally, there were the replacement of two railroad bridges and two roadway bridges, including Mill Street Bridge.”

Modification to the channel and other stabilization efforts improve the creek's ability to move water through the redeveloped corridor. Improving or building new levees and floodwalls provide additional barriers against floodwater in designated areas where the creek has the potential of leaving its banks, while bridge modifications address restrictions that could impede flow.

The interceptor systems address another part of the problem: runoff from the surrounding hillsides of Southwest Boulevard. Large pipelines were installed to collect and redirect stormwater to Turkey Creek that might otherwise flow toward streets and businesses near Southwest Boulevard and the State Line area.

But to install the interceptor systems without impeding the vital railroad traffic that the region’s economy depends on, Corkill stated they resorted to more innovative and less disruptive methods to get the job done.

“We used a tunnel boring machine under the railroad tracks on the interceptors, so that train traffic could keep moving during construction,” she said

The project also includes the new Mill Creek flood warning system, internal drainage features and the Mill Street Up-And-Over, which is designed to accommodate changing water levels while supporting the project's flood risk reduction objectives.

Together, the features form an interconnected network of infrastructure intended to reduce the frequency of flooding while mitigating the severity within the designed project area, according to David Warm, former executive director of the Mid-America Regional Council and ‘Master-of Ceremonies’ for the 2009 tunnel completion commemorative event.

“Turkey Creek has been a particular priority of the two Kansas Cities and the broader metropolitan area, because Turkey Creek is such an important part of our regional economy,” he said. “The corridor is home to approximately 800 businesses, more than 10,000 jobs, major public facilities, interstate highways and railroads — assets that had repeatedly faced flood damage.”

So, as a regional investment the project has provided lasting benefits thus far. As stated previously, it has also provided a window to observe how the system performs under periods of significant rainfall during the construction period.

Local support for the project also reached USACE employees throughout the project’s construction, often in the hours following major storm events. One such response came from Dan Fuhrman, the former owner of Schutte Lumber on the west end of Southwest Boulevard who passed away in 2023, gave his assessment on the system's performance in an email dated May 23, 2016.

“This rain was a good test and is a testimonial of the USACE’s fabulous design. I just love it when a design works ‘REALLY WELL,'" the email said. “Thanks to everyone who has given their time working on this project.”

The following summer, severe storms and heavy rain pummeled the area once again, putting Fuhrman’s observations of the project performance to the test.

“Looking at the available gage records since the lower portion of the channel was completed, the floods of July 27, 2017, August 5, 2017 and July 17, 2025, would have overflowed Turkey Creek without the federal project. There would have been other close calls or more minor damages in 2016 and 2024 as well,” Bitner said.

But, although the project represents a major investment in flood risk mitigation and damage reduction, it does not completely eliminate the possibility of flooding. Extreme weather events can always exceed a system's design capacity, making continued emergency preparedness, awareness and maintenance of the new or improved infrastructure a must.

“While it has been great to see the reduced impacts on the homes and businesses in the area, it is also important to remember that this project only reduces the frequency of flooding and does not fully eliminate the risk,” Bitner said.

Making that clear distinction is important to cultivate understanding of the project's purpose for the local communities Turkey Creek affects. So, the goal was not to make Turkey Creek incapable of flooding, but to reduce the threat posed by a creek that has repeatedly affected the local area and the region, since Kansas City is a major transportation hub for prominent industries that call the metropolitan area home.

The creek and the project's history demonstrate what sustained and effective regional cooperation across local, state and federal agencies accomplishes. Starting from the original tunnel built more than a century ago to the modern network of channels, interceptors and flood risk reduction features, generations of public servants, construction personnel and local partners have worked toward the same objective.

“When you have a large and complex project that is constructed in multiple phases … where each construction contract is like a stand-alone project plus coupled with our rigorous review process, the teams can get very big,” Bitner said.

More specifically, the project required coordination across multiple district disciplines, including project management, engineering, environmental, construction, real estate, economics and legal. Thus, hundreds of district personnel contributed their expertise, carrying knowledge and lessons learned from one phase to the next.

For Bitner, that coordination was central to the project's success.

“The key is keeping the end in mind and making sure all pieces will work together, which the team did really well on Turkey Creek,” Bitner said.

That meant looking beyond individual contracts to understand how each component would connect with the others. Local partners also played an important role. In addition to their financial and property-related responsibilities, they supplied existing infrastructure information, reviewed plans and shared observations about how the project performed under changing conditions.

“As construction was drawn out over many years, the sponsors' observations of how the project performed also helped identify potential operational challenges that we were able to directly overcome or better account for,” Bitner said.

Two of those partners were the Missouri and Associated River Coalition and the Kansas City Industrial Council. For Corkill, who is now the branch chief for the district’s Project Management Section, their role in ensuring what project elements get funded and the project reaches the finish line, should not go unnoticed.

“They worked with USACE, The City of Kansas City, Missouri, the United Government of Wyandotte County and local businesses to bring the support this project needed. Without [organizations like] them, these projects are harder to complete,” Corkill said.

A project built in phases culminates in celebration

Construction proceeded through multiple contracts and phases, with the final construction phase being the natural reach contract in 2024-25.

According to the project timeline and budget, the total cost was $161 million. Corkill detailed what moved other elements of the project forward after the underground tunnel rehabilitation was complete.

“The project took off with significant funding from American Recovery and Reinvestment Act of 2009,” she said. “We were able to complete the walled channel that went under a widened railroad bridge, and made significant improvements to flood risk reduction before the [entire] project was complete.”

Bitner then explained what the extensive project work and improvements to flood risk reduction were designed to safeguard.

“When counting those working in the area, the population at risk is over 30,000 people and approximately 205 residential and commercial structures valued at $232 million,” he said.

According to John Grothaus, former chief of Plan Formulation and a longtime manager on the project before he recently retired, the hallmark of the project was the strong partnership between multiple agencies at federal, local and state levels that accomplished it.

“USACE, the City of Kansas City, Missouri, Unified Government of Wyandotte County and the City of Kansas City, Kansas, the Kansas Department of Transportation, BNSF Railroad and the business community all made a commitment to work together to bring critical flood relief to the corridor,” he said.

But most importantly, Grothaus intimated how amicable collaboration between public and private entities helped benefit the public in ways they often don’t take into account.

“This team effort and close coordination saved the taxpayers a lot of money, too,” he said. At the project’s ribbon-cutting ceremony on Wednesday, Oct. 21, on the banks of Turkey Creek, Rep. Sharice Davids of Kansas’ 3rd Congressional District emphasized that the investment extends beyond the infrastructure itself.

“Now what we’re going to be talking about is hundreds of homes and businesses that have a little less stress in their lives because they don’t have to worry every single time there’s major rain,” Davids said.

For Nicole Tauheed of KC Water, the milestone also carried a personal meaning since she grew up in the Rosedale neighborhood of Kansas City, Kansas, in the shadow of Turkey Creek.

She said she remembered the effects the 1993 and 1998 floods had on many Southwest Boulevard businesses her family frequented. Decades later, she spoke to what it meant to her to help manage the project.

“I saw the power of water. So, when I joined KC Water five years ago and had the opportunity to co-manage this project, I jumped at the chance because, for me, being involved in this project is protecting home,” Tauheed said. Deputy commander of the Kansas City District, U.S. Army Corps of Engineers, Lt. Col. John Myers, also spoke at the ceremony. While using his time to highlight the many complexities of the project, he also expressed extreme gratitude to those who helped USACE get the job done.

“I want to give a special thank you to our non-federal sponsors, the City of Kansas City, Missouri, the Unified Government of Wyandotte County, and the City of Kansas City, Kansas. Your leadership has been essential throughout the life of this project,” he said.

Former Kansas City, Missouri, Mayor, Emanuel Cleaver, was one of the last speakers to close out the ceremony. Reflecting on his own experience of being the only mayor to govern through two 500-year floods while in office, Cleaver pointed to the dedication displayed by all to reach this milestone.

“We have just mitigated one of the most troubling projects … that has created devastation in our community,” Cleaver said. “All of you ought to be very proud and pleased because of the one thing [about this project] I think we can export around the country, [is showing] that people are working together.”

Continuous years of actual flooding or the mere threat of it helped spur calls for action. Now, the completion of the Turkey Creek Flood Damage Reduction Project stands as a reminder that major infrastructure takes more than engineering and funding. It takes sustained commitment from agencies, elected officials, workers, and communities willing to keep working together toward a shared goal.

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.

Share this page:

Advanced Search Options

Search for:

Search scope:

Type:

Search in:

Date range:

The last

Sort by:

Sign up for:

Banking Press Releases

The daily local news briefing you can trust. Every day. Subscribe now.

By signing up, you agree to our Terms & Conditions.